Pacific Motorway Upgrade (Watland Street to Sports Drive)
Project Outline
Products / Services
Bored Piles
Widening the M1 up to 4 southbound and Northbound lanes between north of Exit 19 (Rochedale Road) to Logan Road.
Scope of Works
224no Bored piles total completed over 3.5year duration
7 Bridges – 134no. Bored Piles with Permanent and Temporary Casing (750mm to 1800mm diameter)
3 Retaining Walls – 62no. Bored Piles with Permanent and Temporary Casing (600mm to 1200mm diameter)
14 Gantry Foundations – 28no. Bored piles with Permanent Casing (750mm to 1050mm diameter)