Cooroy to Curragh Stage C and D
Project Outline
Products / Services
Bored Piles
The project Cooroy to Curragh Stage C and D are two sections of the project that involves a 62km realignment and upgrade of the Bruce Highway to 4 lanes between Cooroy and Curra. The Section C delivered a new 4-lane divided highway between the new section of the 10km highway between Traveston and Woondum, and Section D – Package 2 is the upgrade of the final section of Bruce Highway delivering a new 18km, 4-lane divided highway between Sandy Creek Road and Curra.
Scope of Works
Avopiling QLD is contracted to built bored foundation
Section C – 7 bridges (commenced June 2016, completed December 2016), Total piles - 132 nos x 1200mm diameter (permanent liners), Depths up to 18m.
Section D- 12 Bridges (commenced November 2021, completed March 2023), Total piles- 170 nos (permanent liners)
1050mm dia piles:- 04 nos
1200mm dia piles- 116nos
1350mm dia piles- 06 nos
1500mm dia piles- 28nos
1800mm dia piles:- 16nos
Pile length/depth -up to 26.0m
Industry leading techniques and equipment